Planning Matters continued




        Country Club or the finger canal area east of Bayview  • The estimated cost of laying the required conduit leading
        could be included. Our neighborhood is large in         from the public right of way and ending at the meter box
        comparison to the neighborhoods currently signed up,    located on the Parcel if Owner has agreed in writing to
        making a partial program possible.                      permit City’s Contractor to construct the conduit on the Parcel.
                                                              • The estimated cost of restoration of Parcel damage as a
           City prepares 90% design plans. The cost of the plans,
        currently estimated at about $550 per property, will be   result of the installation of the conduit on the Parcel if
        billed to residents over a 24-month period at about $25   Owner has agreed in writing to permit City’s Contractor
        per month.                                              to construct the conduit on the Parcel.
                                                              • Estimated costs of obtaining any required Easements or
           A cost estimate for the project will be prepared. The cost   other conveyances or Agreements.
        includes the following:                               • Estimated cost of a Coordinating Consultant to coordinate
        • The preliminary estimate for the cost of Preliminary Plans  all activities and prepare all documents necessary to bring
          and final Plans and Specifications and Contract       the UULA to the City Commission for a public hearing to
          Documents provided by FP&L and the other utilities or such  consider adoption of a Final UULA Assessment.
          other consultant capable of providing such documents.  • Estimated terms for payment of the special assessment.
        • Estimated construction cost.                        4. Once the design plans are complete, a vote of property
        • Estimated right-of-way restoration costs including repaving  owners will be held in which approval of 70% of property
          of the rights-of-way and restoring sidewalks, landscaping  owners in an area who return a ballot - not 70% of
          and drainage within the rights-of-way.