Planning Matters continued
Country Club or the finger canal area east of Bayview • The estimated cost of laying the required conduit leading
could be included. Our neighborhood is large in from the public right of way and ending at the meter box
comparison to the neighborhoods currently signed up, located on the Parcel if Owner has agreed in writing to
making a partial program possible. permit City’s Contractor to construct the conduit on the Parcel.
• The estimated cost of restoration of Parcel damage as a
City prepares 90% design plans. The cost of the plans,
currently estimated at about $550 per property, will be result of the installation of the conduit on the Parcel if
billed to residents over a 24-month period at about $25 Owner has agreed in writing to permit City’s Contractor
per month. to construct the conduit on the Parcel.
• Estimated costs of obtaining any required Easements or
A cost estimate for the project will be prepared. The cost other conveyances or Agreements.
includes the following: • Estimated cost of a Coordinating Consultant to coordinate
• The preliminary estimate for the cost of Preliminary Plans all activities and prepare all documents necessary to bring
and final Plans and Specifications and Contract the UULA to the City Commission for a public hearing to
Documents provided by FP&L and the other utilities or such consider adoption of a Final UULA Assessment.
other consultant capable of providing such documents. • Estimated terms for payment of the special assessment.
• Estimated construction cost. 4. Once the design plans are complete, a vote of property
• Estimated right-of-way restoration costs including repaving owners will be held in which approval of 70% of property
of the rights-of-way and restoring sidewalks, landscaping owners in an area who return a ballot - not 70% of
and drainage within the rights-of-way.