Page 22 - Layout 1
P. 22
Fiveash Water Treatment Plan Facility
Concrete Restore
This project is to assess the concrete surfaces and structures
at the Water Treatment Plants for failures. The work will
create the bid specs for concrete repairs, oversee the bid
process, and the construction inspection services.
Utilities Storage Building
This project is to construct a prefabricated steel building
such as a "Butler" building to store equipment and
materials for use in utilities projects. The pipe yard/depot
at the Public Works compound is at its maximum capacity.
There are no available covered storage spaces to keep
components out of the weather.
Peele Dixie R&R
Peele-Dixie Treatment Plant - renewal and/or replacement
of miscellaneous equipment, structures, pipes and other
features critical to the continued safe, reliable, efficient,
and compliant operation of the plant.
Coral Ridge Isles
The project includes the rehabilitation of the sanitary sewer
collection system throughout Basin B-13. This includes, but
not limited to point repairs, minor road restoration,
landscaping, the use of trenchless technologies to repair
sewer system components such as lining of gravity sewers,
manholes, and sewer laterals. Work also includes pre and
post television survey, flow monitoring, traffic control and
site restoration.
Water Distribution Service
This project will replace the existing Water Pressure
SCADA system with a new system that will monitor water
system pressure, chlorine residual, pH, turbidity and
conductivity. This system will interface with the existing
water plant control system and have the data recorded.
Eight new panels will be installed at various locations in
the city's water distribution system.
Fiveash Water Treatment Plant
Disinfection Improvements The City of Fort Lauderdale Public Works
The Fiveash Reliability Upgrades (P11593 & P10508) Department has launched "Go Big, Go Fast!”
project was added to the Disinfection System Replacement
a comprehensive initiative designed to improve,
project (P11589) for bidding and construction, so that one upgrade, and enhance our City's wastewater
contractor will be responsible for use of the limited free
system, strengthen our infrastructure, and
spaces at the plant. Both projects will be constructed at the
same time. move us closer to achieving our shared
community-wide vision of becoming
Fiveash Water Treatment Plant Hydrotreators “The City You Never Want To Leave.”
This project includes the replacement of 30" diameter steel
fabricated flagned fitting and associated valves and For the latest project updates
couplings, replacement of air release valves, replacement (issued weekly), please visit
of sump pump and associated piping for Hydrotreators 3 & www.fortlauderdale.gov/gobiggofast.
4 at the Fiveash Water Treatment Plant.
20 The Landings & Bay Colony